10/31/22
Construction of the Rain Gardens project began September 12th. The contractor, selected by competitive bid, is California Constructores from San Pablo.
Work completed so far includes surveying, utility locating, cleaning out of the old drainage ditch, saw cutting and removal of old concrete, construction of the two bioretention basins, placing subdrain and permeable backfill in the bioretention basins, new storm drain infrastructure at the Fred Jackson Way and Brookside Drive intersection consisting of a new catch basin and new pipe tying into the existing storm drain system, and a new storm drain crossing Fred Jackson Way and tying into the existing storm drain system there.