February 16, 2024
Concrete foundations and slabs have all been poured now for the Phase 2 buildings, and the walls are taking shape!
Main Greenhouse CMU walls complete; next step will be the superstructure
Tool Shed and Staff Break Room walls going up!
Watershed Workshop slab poured
Shade House slab poured